Plan & Prep Phase|Step 4 of 33
Create Realistic Timeline
A well-planned timeline prevents chaos. Coordinate contractors, deliveries, and your own availability for smooth execution.
Time Required
1-2 hours
Cost
$0
Difficulty
Easy
Sample Timeline by Scope
| Project Scope | Timeline |
|---|---|
| Paint & hardware only | 1-2 weekends |
| Countertops + paint | 1-2 weeks |
| Full update (no layout change) | 2-4 weeks |
| Update + appliance replacement | 3-4 weeks |
Typical Week-by-Week Flow
1
Week 1: Demo & Prep
Remove old countertops, prep cabinet surfaces, paint prep, electrical prep. Set up temporary kitchen.
2
Week 2: Major Installs
Countertop templating and installation, major appliance delivery and hookup, cabinet painting if applicable.
3
Week 3: Plumbing & Electrical
Sink and faucet installation, disposal hookup, outlets and switches, under-cabinet lighting.
4
Week 4: Finishing
Backsplash install and grouting, paint touch-ups, hardware installation, final cleanup and punch list.
Lead Times to Factor In
- Countertops: 2-4 weeks from template to install
- Custom cabinets/doors: 4-8 weeks if ordering
- Appliances: 1-4 weeks depending on availability
- Contractor scheduling: 2-6 weeks for good ones
- Tile/backsplash materials: 1-2 weeks if not in stock
- Permit approval: 1-3 weeks if required
Pro Tips
- •Order materials early: Supply chain issues are real. Order 4-6 weeks ahead.
- •Build in buffer days: Add 2-3 extra days per week. Delays happen.
- •Coordinate dependencies: Counters go in before sink. Sink before plumbing. Plan the sequence.
- •Set up a temporary kitchen: Microwave, coffee maker, and paper plates make life bearable.