Step 34 of 67Demolition Phase

How to Perform Selective Demolition

Selective demolition is the careful art of removing exactly what needs to go while protecting everything that stays. Unlike total gut jobs, this surgical approach requires precision planning to avoid costly damage to systems and structures you want to preserve.

Quick Summary

Typical cost

$5,000 - $25,000

Timeline

5-14 days

Cost per sq ft

$5 - $15

Why This Matters

Demolition sets the stage for everything that follows. Done well, it creates a clean slate exactly where you need one while preserving the bones of your home. Done poorly, it creates expensive problems: damaged plumbing that floods during construction, severed electrical circuits, cracked foundation elements, or destroyed finishes you intended to keep.

The key to successful selective demo is clear communication. Every worker needs to know exactly what stays and what goes. One swing of a sledgehammer can destroy a $3,000 window or sever a load-bearing beam. This phase requires constant attention and clear marking.

This is also when you'll discover hidden conditions. Every old home has surprises behind the walls - some good (original hardwood floors under carpet), some bad (hidden water damage, inadequate framing). Expect the unexpected and keep your contingency fund ready.

Step-by-Step Guide

1. Pre-Demo Walkthrough

Before any demolition begins, walk through the entire project with your general contractor and the demo crew. Identify every element that stays vs. goes.

Create clear documentation:

  • Mark walls to be removed with spray paint (typically red)
  • Mark elements to protect with different color (typically green/blue)
  • Provide marked-up floor plans showing demo scope
  • Take dated photos of all areas before demo starts
  • Note locations of utilities, load-bearing walls, and sensitive systems

2. Protect What Stays

Before demolition begins, protect all elements that will remain. Demo creates tremendous dust, debris, and vibration that damages unprotected surfaces.

Physical Protection

  • Cover floors with ram board or heavy plastic
  • Wrap windows with plastic sheeting
  • Cover door frames with foam board
  • Seal HVAC vents to prevent dust spread
  • Protect fixtures with moving blankets

System Protection

  • Mark electrical lines in walls
  • Identify and mark plumbing runs
  • Tag gas lines clearly
  • Protect HVAC ducts and equipment
  • Secure low-voltage wiring locations

3. Disconnect Utilities

Before any structural demolition, all utilities in the work area must be properly disconnected by licensed professionals.

Electrical:Licensed electrician disconnects circuits in demo areas. Verify with voltage tester before cutting. Lock out panel if necessary.
Plumbing:Shut off water supply, drain lines, cap exposed pipes. Identify drain and vent locations to avoid sewer gas issues.
Gas:Gas company or licensed plumber shuts off and caps gas lines before demo. Never attempt to disconnect gas yourself.
HVAC:Disconnect ductwork being removed. Seal remaining openings to prevent debris in system.

4. Remove Fixtures First

Start with careful removal of fixtures and finish materials. Many can be salvaged for donation or reuse elsewhere.

Removal sequence:

  1. 1.Appliances (donate functional units to Habitat ReStore)
  2. 2.Plumbing fixtures (toilets, sinks, tubs - salvageable if undamaged)
  3. 3.Light fixtures and ceiling fans
  4. 4.Cabinets and countertops (can often be reused or donated)
  5. 5.Doors and hardware (antique hardware is valuable)
  6. 6.Trim and molding (save for matching if partial renovation)
  7. 7.Flooring (hardwood can sometimes be salvaged)

5. Remove Drywall and Finishes

With fixtures out, remove wall and ceiling finishes to expose framing. This reveals the true condition of structures and systems.

Critical reminder:

Stop if you encounter anything unexpected: suspected mold, unusual insulation (vermiculite could contain asbestos), knob-and-tube wiring, or structural damage. Investigate before proceeding.

  • Cut drywall carefully around areas that stay
  • Remove ceiling drywall before walls (falls on floor, not you)
  • Cut at stud locations for clean edges
  • Score at transition lines with utility knife
  • Remove insulation and bag separately from drywall

6. Demolish Non-Structural Walls

With finishes removed, take down non-structural walls per your architectural plans. Never assume a wall is non-structural - verify first.

Signs of Non-Load-Bearing

  • Runs parallel to floor/ceiling joists
  • No wall directly above on upper floor
  • Single top plate (not doubled)
  • Confirmed by engineer/architect

Likely Load-Bearing (Never DIY)

  • Runs perpendicular to joists
  • Wall continues through multiple floors
  • Located at center of structure
  • Contains posts or beams

7. Address Load-Bearing Walls (Per Engineering)

Removing load-bearing walls requires temporary shoring and installation of new support beams. This must follow structural engineering plans exactly.

Load-bearing wall removal process:

  1. 1. Install temporary support posts and beams on both sides
  2. 2. Transfer load to temporary structure
  3. 3. Remove existing wall carefully
  4. 4. Install engineered beam per specifications
  5. 5. Install permanent support posts with proper bearing
  6. 6. Remove temporary shoring only after beam is secured
  7. 7. Framing inspection required before proceeding

8. Continuous Debris Management

Demo generates enormous amounts of debris. Manage it continuously to maintain safe working conditions and keep the project moving.

  • Clear debris daily - don't let it pile up
  • Schedule dumpster exchanges before current one fills
  • Separate materials: wood, metal, concrete, hazmat
  • Keep pathways clear for safety
  • Protect neighbors from dust and debris

Pro Tips

  • Be there for day one. The first day of demo is critical. Be present to answer questions and catch misunderstandings before they become expensive mistakes.
  • Document everything behind walls. Once walls are open, photograph all plumbing, electrical, and structural elements. This documentation is invaluable for future work.
  • Salvage strategically. Antique hardware, original trim, hardwood flooring, and working fixtures have value. Coordinate with Habitat ReStore for donation pickup and tax deduction.
  • Expect surprises. Almost every remodel finds something unexpected: hidden damage, code violations, or previous botched repairs. Document discoveries immediately and discuss implications.

Common Mistakes to Avoid

Removing walls without verifying load path

Never assume a wall is non-structural. Even experienced contractors sometimes misjudge. Always verify with structural engineer before removing any wall, especially those perpendicular to floor joists or in the center of the structure.

Inadequate utility disconnection

Cutting into a wall with live electrical or pressurized water creates dangerous and expensive problems. Always verify utilities are properly disconnected and capped before demo begins in any area.

Rushing through protection

Taking 30 minutes to properly protect a $5,000 hardwood floor saves thousands in refinishing. Demo is fast and violent - protection must be comprehensive and secure before work begins.

Not documenting hidden conditions

Once walls are open, you see what's really there. Take extensive photos and video of all plumbing, electrical, structural, and any damage discovered. This documentation is essential for planning and disputes.

Allowing debris to accumulate

Piles of debris create safety hazards, slow work, and can damage surfaces underneath. Clear debris daily and keep the dumpster schedule aggressive. A full dumpster stops progress.

Demolition Cost Breakdown

ScopeCost RangeTimeline
Light demo (finishes only)$2,000-$5,0002-4 days
Moderate selective demo$5,000-$12,0005-8 days
Extensive selective demo$12,000-$25,00010-14 days
Complete gut (structure only remains)$15,000-$35,0007-14 days
Load-bearing wall removal (each)$1,500-$5,0001-2 days
Debris hauling (per dumpster)$400-$800-

Frequently Asked Questions

What is selective demolition?

Selective demolition (also called soft demo or surgical demolition) is the careful removal of specific building components while protecting and preserving elements that will remain. Unlike full demolition, selective demo requires precision to avoid damaging structures and systems that are staying.

How much does selective demolition cost?

Selective demolition typically costs $5-$15 per square foot for a whole-home remodel, or $5,000-$25,000 total depending on scope and complexity. Factors include accessibility, disposal requirements, and protection requirements for remaining elements.

How long does demolition take for a whole house?

Selective demolition for a whole-home remodel typically takes 5-14 days depending on home size and scope. A 2,000 sq ft home with extensive selective demo might take 7-10 days. Plan for dumpster exchanges every 2-3 days during active demo.

Should I be present during demolition?

Yes, you or your project manager should be present at the start of demolition to walk through the scope with the crew. Daily presence isn't necessary if you trust your contractor, but check in frequently. Request daily photos and have a clear communication channel.

Can I do demolition myself to save money?

Some homeowners do limited demo (removing cabinets, flooring, or non-structural elements) to save $2,000-$5,000. However, this comes with risks: injury, damage to systems, and project delays. Never do structural demolition yourself.

Ready for the Next Step?

As demolition progresses, you'll need to manage the substantial debris it generates. Coordinating dumpster exchanges and material recycling keeps the project moving efficiently.

Related Guides