Budget PhaseStep 18 of 62

How to Create a Comprehensive Budget for Your Whole-Home Remodel

A realistic budget is the foundation of a successful remodel. Underestimate, and you'll face impossible choices mid-project. Overestimate, and you miss opportunities. This guide helps you account for every category of cost—including the ones most homeowners forget.

Quick Summary

Time needed

4-8 hours

Difficulty

Moderate (many variables)

Typical total budget

$150,000-$750,000+

Why Budget Comprehensively

Most homeowners significantly underestimate whole-home remodel costs. They budget for construction but forget about design fees, permits, temporary housing, storage, and the inevitable contingency needs. These "extras" can add 30-50% to construction costs.

Running out of money mid-project is devastating. You're stuck with a partially finished home, no way to live there, and no funds to complete the work. Comprehensive budgeting prevents this nightmare.

The True Cost Reality

If your construction bid is $300,000, your total project cost is likely:

  • • Construction: $300,000
  • • Design fees (10%): $30,000
  • • Permits and fees (3%): $9,000
  • • Temporary housing (12 months): $36,000
  • • Storage and moving: $6,000
  • • Contingency (15%): $45,000
  • • New furniture/décor: $20,000
  • Total: ~$446,000
  • Prevents mid-project crisis: Running out of money with half-finished work is a nightmare scenario.
  • Enables informed decisions: Know true costs before committing so you can make realistic choices.
  • Allows proper financing: Secure adequate funding upfront rather than scrambling for more later.
  • Reduces stress: Financial uncertainty makes an already stressful process worse.
  • Protects relationships: Money problems during remodels strain marriages and contractor relationships.

Budget Categories

A complete whole-home remodel budget includes these major categories. Each requires careful estimation.

Construction Costs (60-65% of total)

The contractor bid for demolition, framing, MEP, finishes, and labor. This is the core but not the complete picture.

Typical Cost Ranges (2024):

Basic renovation$100-$200/sq ft
Mid-range renovation$200-$350/sq ft
High-end renovation$350-$500/sq ft
Luxury/custom renovation$500-$1,000+/sq ft

Costs vary significantly by location. Coastal cities and major metros are higher.

Design Fees (8-15% of construction)

Architecture, engineering, interior design—the professional fees that create your construction documents.

Typical Design Costs:

  • • Architect: 8-15% of construction cost
  • • Structural engineer: $2,000-$10,000
  • • Interior designer: 10-20% of furnishing budget or hourly
  • • Landscape architect: $5,000-$15,000 (if applicable)
  • • 3D renderings: $1,500-$5,000

Permits and Fees (2-4% of construction)

Government fees for permits, inspections, and regulatory compliance.

Typical Permit Costs:

  • • Building permit: $2,000-$15,000+
  • • Plan check fees: $1,000-$5,000
  • • Utility connection fees: $500-$3,000
  • • School/impact fees: $0-$20,000 (varies by jurisdiction)
  • • HOA fees: $500-$2,000 (if applicable)

Temporary Housing (5-10% of total)

Living somewhere else during construction. Often underestimated or forgotten entirely.

Housing Costs:

  • • Rental apartment: $2,000-$5,000/month × 8-14 months
  • • Extended stay hotel: $3,000-$6,000/month
  • • Additional utilities: $200-$400/month
  • • Extra commuting costs: $100-$300/month

Budget for 2-3 months longer than projected timeline

Moving and Storage (1-2% of total)

Moving belongings out, storing them, and moving back in.

Typical Costs:

  • • Climate-controlled storage: $200-$500/month × 10-14 months
  • • Professional movers (out): $1,000-$3,000
  • • Professional movers (back): $1,000-$3,000
  • • Packing supplies: $200-$500

Contingency (15-20% of construction)

Unexpected costs that WILL arise. This isn't optional padding—it's essential protection.

Common Contingency Uses:

  • • Hidden water damage discovered during demo
  • • Structural issues not visible in plans
  • • Code upgrades required by inspector
  • • Material price increases during long project
  • • Design changes you request
  • • Weather or supply chain delays
Critical: Don't use contingency for upgrades. It's insurance against surprises, not a slush fund for nicer countertops. Keep it reserved until the project is complete.

Post-Construction Costs (5-10% of total)

Finishing touches after the contractor leaves.

Don't Forget:

  • • Window treatments: $3,000-$15,000+
  • • New furniture: $10,000-$50,000+
  • • Landscaping repair: $2,000-$10,000
  • • Professional cleaning: $500-$1,500
  • • Smart home setup/programming: $500-$3,000
  • • Art and accessories: $2,000-$10,000

Sample Budget Breakdown

Here's how a $300,000 construction budget translates to total project cost.

Mid-Range Whole-Home Remodel (2,500 sq ft)

Construction (contractor bid)$300,000
Architect (10%)$30,000
Interior designer$15,000
Structural engineer$5,000
Permits and fees$10,000
Temporary housing (12 mo × $3,000)$36,000
Storage and moving$8,000
Contingency (15%)$45,000
Furniture and window treatments$25,000
Landscaping repair$5,000
Miscellaneous (cleaning, setup)$3,000
Total Project Budget$482,000

Note: $300,000 construction bid → $482,000 total (1.6× multiplier)

Common Mistakes to Avoid

Budgeting only for construction

Why it's a problem: Design, permits, housing, and contingency add 30-50% to construction costs

What to do instead: Budget for TOTAL project cost using the 1.5-1.6× multiplier on construction.

Inadequate contingency

Why it's a problem: Surprises are guaranteed in whole-home remodels, especially older homes

What to do instead: 15-20% contingency minimum. Pre-1980 homes may need 25%.

Underestimating timeline (and housing costs)

Why it's a problem: Projects almost always take longer than projected

What to do instead: Add 2-3 months to projected timeline when budgeting temporary housing.

Forgetting post-construction costs

Why it's a problem: Empty rooms need furniture; torn-up yards need landscaping

What to do instead: Budget for everything needed to actually live in and enjoy the finished home.

Using contingency for upgrades

Why it's a problem: Leaves you exposed when real surprises occur

What to do instead: Keep contingency sacred. Budget upgrades separately or cut from original scope.

Budget Tracking Tips

Create a Detailed Spreadsheet

Track every cost by category with columns for: budgeted amount, actual spent, remaining, and notes. Update it weekly minimum.

Track Change Orders Religiously

Every change should be documented with cost before approving. Small changes add up fast. Review change order total weekly.

Set Warning Thresholds

Create alerts when any category hits 80% of budget. This gives time to adjust before overrunning. Review total spending vs. percentage complete.

Keep Contingency Separate

Don't let contingency blend into general budget. Track it separately. Document every contingency use with justification.

Frequently Asked Questions

How much does a whole-home remodel cost?

Typically $100-$400+ per sq ft for construction, depending on scope and location. For a 2,500 sq ft home, expect $250,000-$750,000+ for construction—add 40-60% for total project cost including design, permits, housing, and contingency.

What percentage should I budget for contingency?

15-20% of construction costs minimum. Older homes (pre-1980) should budget 20-25% due to likely hidden issues. This isn't optional—it's essential protection.

What costs do people forget when budgeting?

Temporary housing (8-14 months), storage and moving, design fees (8-15%), permits, post-construction furniture/window treatments, and landscaping repair. These can add 40-60% to construction cost.

Should I tell my contractor my budget?

Yes, share your realistic construction budget so they can design appropriate solutions. Don't share your contingency—keep that as reserve.

How do I track spending during a remodel?

Detailed spreadsheet with categories matching your budget. Record every payment and change order. Review weekly. Set alerts at 80% of category budgets. Consider construction management software for large projects.

Ready for the Next Step?

With your comprehensive budget established, it's time to get detailed bids from contractors. This will validate your budget assumptions and help you select the right partner.