Step 3 of 37Plan & Permits

Apply for Permits

Navigating the permit process for your attic conversion. This major renovation requires building, electrical, plumbing, and HVAC permits.

2-6 weeks
Approval Time
$500-2,000
Permit Fees
Medium
Difficulty Level

Why Permits Are Non-Negotiable

Attic conversions are major structural modifications that require proper permits. Building without permits can result in fines, required demolition, voided homeowner's insurance, and serious problems when selling your home. Permits ensure your work meets safety codes for fire protection, structural integrity, electrical safety, and energy efficiency. While the permit process takes time, it protects your investment and your family's safety. Inspections catch problems early when they're easier and cheaper to fix.

Documents You'll Need

Site/Plot Plan
$0-50
Floor Plans
$200-1,000
Structural Report
$300-800
Contractor License
Free
Insurance Certs
Free
Energy Calcs
$100-300
Title/Deed
Free
HOA Approval
If applicable

Step-by-Step Permit Process

1

Research Your Local Requirements

Before preparing your application, understand what your jurisdiction requires:

  • Visit your city/county building department website
  • Schedule a pre-application meeting if available - many departments offer free consultations
  • Ask about specific requirements for attic conversions in your area
  • Check if online submission is available or if in-person is required
2

Prepare Your Plans and Documents

Gather all required documentation before submitting:

Floor Plans
To-scale drawings showing existing and proposed layout, with dimensions, room labels, and egress windows.
Structural Engineering Report
PE-stamped drawings and calculations for floor reinforcement and any roof modifications.
Electrical/Mechanical Plans
Layout of outlets, switches, HVAC, and plumbing locations. May require separate permits.
Site Plan
Property survey showing setbacks, any exterior changes like dormer windows.
3

Complete Application Forms

Fill out all required permit applications carefully:

Building permit application (primary)
Electrical permit application
Plumbing permit (if adding bathroom)
Mechanical/HVAC permit
Property owner authorization
Contractor information

Pro Tip: Double-check your project valuation - it affects permit fees. Include materials and labor but don't over-inflate. Underestimating can result in penalties.

4

Submit and Pay Fees

Submit your complete application package with required fees:

  • Plan review fee: Often 65% of total permit fee, due at submission
  • Building permit: Usually 1-2% of project value ($250-1,000+)
  • Trade permits: $50-200 each for electrical, plumbing, HVAC
  • Impact fees: Some areas charge for adding living space
5

Respond to Plan Review Comments

Plan reviewers may request changes or clarifications:

  • Check status weekly - many departments have online portals
  • Respond to comments promptly to avoid going to the back of the queue
  • If you don't understand a comment, call the reviewer directly
  • Revised plans may require additional review time

Note: Plan review can take 2-6 weeks depending on backlog and complexity. Budget this time into your project schedule.

6

Receive and Post Permits

Once approved, pick up your permits and prepare for inspections:

  • Pay remaining permit fees (if balance due)
  • Get stamped approved plans - keep one set at job site
  • Post permit card in visible window before starting work
  • Note inspection requirements and scheduling procedures

Required Inspections

InspectionWhen
Framing/StructuralAfter framing, before insulation
Rough ElectricalAfter wiring, before drywall
Rough PlumbingAfter rough-in, before covering
HVAC RoughAfter ductwork, before covering
InsulationAfter install, before drywall
FinalAfter all work complete

Pro Tips

  • Submit early - permit backlogs can add weeks to your timeline
  • Use the same architect or engineer for revisions - they understand the project
  • Keep copies of everything - approved plans, permits, inspection cards
  • Schedule inspections 24-48 hours in advance to avoid delays
  • Be present for inspections when possible - you can ask questions and learn

Frequently Asked Questions

How much do attic conversion permits cost?

Permit costs vary by location and project scope, typically ranging from $500-$2,000. Most jurisdictions charge based on project value (often 1-2% of construction cost) plus flat fees for plan review. Electrical, plumbing, and mechanical permits may be separate additional fees of $50-$200 each.

How long does the permit approval process take?

The permit process typically takes 2-6 weeks for initial review. Simple projects may be approved faster with over-the-counter permits. Complex projects requiring structural changes or variances can take 2-3 months. Building departments are often backlogged, so submit early and follow up regularly.

What happens if I build without a permit?

Building without permits can result in fines ($500-$5,000+), required demolition of work, and stop-work orders. Unpermitted work can void insurance coverage, create liability issues, and cause problems when selling your home. Most buyers and lenders require permits for major renovations.

Do I need an architect for attic conversion permits?

Requirements vary by jurisdiction and project scope. Many areas require a licensed architect or engineer for structural modifications, dormers, or projects over a certain size. Some allow homeowner-drawn plans for simpler conversions. Check with your building department early to understand their requirements.